DOSH Design Verification for Imported Pressure Vessels

DOSH design verification (Verifikasi Reka Bentuk) is a mandatory approval required before any new, unused pressure vessel can enter Malaysia. It’s required under the Occupational Safety and Health (Plant Requiring Certificate of Fitness) Regulation 2024, effective 1 June 2024. Applications go through DOSH’s MySKUD system. Vessels fall into two categories based on internal diameter (inch) × design pressure (psig) — 3,000 psig.in and above, or below — which determines whether Authorized Inspection Body (AIB) certification is required. DOSH’s stated processing time is 15 working days with a complete application.

What is DOSH design verification?

Which pressure vessels need this?

  • Scope: new, never used, no deterioration
  • “Pressure vessel” (bejana tekanan) — any closed vessel operating above or below atmospheric pressure. Examples: air receiver tanks, shell-and-tube heat exchangers, retorts
  • “Fired pressure vessel” (bejana tekanan berapi / BTB) — has a heating element that doesn’t generate steam. Examples: thermal oil heater, hot water boiler, fired heater, electrical heater

  • Two categories, based on internal diameter (inch) × design pressure (psig):
    • ID × Design Pressure ≥ 3,000 psig.in — design drawings and calculations must be verified by an AIB, with a signed AIB certificate submitted
    • ID × Design Pressure < 3,000 psig.in — AIB confirmation required only where the design standard or the vessel owner requires it
  • Some vessel types are excluded under the Regulation’s Second Schedule

What design standards does DOSH accept?

  • DOSH only recognizes design codes listed in the Regulation’s Forth Schedule current edition or amendment
  • Most common: ASME Boiler and Pressure Vessel Code, Section VIII, Division 1
  • China’s national GB standard is not recognized by DOSH for pressure vessel design verification
  • A Chinese-manufactured vessel is not the issue — but it must be designed and built to a DOSH-recognized standard (typically ASME VIII Division 1), not GB

What documents does DOSH require?

  • Design drawings — legible, landscape orientation, includes the nameplate drawing, in Bahasa Malaysia or English, sized so details aren’t cramped
  • Design calculations / analysis — prepared to the recognized code’s current edition
  • Supporting documents — AIB certificate (≥ 3,000 psig.in) or AIB confirmation as required by the standard/owner (< 3,000 psig.in)

  • Design data on the drawings: design and operating pressure/temperature, test pressure and test type, MDMT, MAWP, PWHT, radiography degree, joint efficiency, corrosion allowance, flange rating
  • Bill of materials, nozzle and flange schedules, detailed drawings of major components (nozzle, flange, tubesheet), weld details, support/skirt/lug dimensions

How long does it take?

  • DOSH’s stated customer charter: 15 working days from a complete application
  • In MESH’s experience: 15–30 working days, sometimes longer
  • Main drivers of delay: equipment complexity, how closely the design already complies with a recognized standard, and document quality
  • Incomplete documentation is the single biggest cause of delay

MESH’s professional service — advising on requirements, reviewing supplier documentation, submitting to DOSH, and following up through to approval — is quoted case by case, based on the vessel’s complexity and scope of work involved.

When should you apply?

  • Apply while the vessel design is still on paper — before fabrication, and before the vessel is shipped to Malaysia
  • Common mistake: suppliers and end-users only start the process after the vessel is already manufactured, shipped, and installed on-site
  • Consequence: the vessel generally can’t be legally operated until verification is complete, and standards gaps are far harder to fix once the vessel is a physical, installed asset
  • Applying early gives room to correct compliance gaps cheaply, before they become a site problem

What should end-users specify when purchasing?

  • State the required design standard (typically ASME VIII Division 1) in the purchase terms
  • Require full design drawings, calculations, and AIB certification (where applicable) as part of the purchase agreement — not requested after the fact
  • Without this, suppliers are often never told DOSH’s requirements exist, and the right documentation is never prepared

Why do most overseas suppliers and end-users use a local consultant?

  • Foreign-based manufacturers and suppliers typically have no Malaysian entity and aren’t familiar with DOSH’s requirements or the MySKUD system
  • MESH’s role:
    • Advise on requirements, realistic timeline, and what the application involves
    • Advise on acceptable design standards and when AIB certification is required
    • Review supplier documentation against DOSH’s requirements before submission, to reduce rejection risk
    • Submit via MySKUD and coordinate with DOSH through to approval
    • Liaise directly with manufacturers, suppliers, and end-users throughout
  • Note: MESH does not coordinate directly with the AIB — that relationship sits between the client/manufacturer and the AIB itself

MESH has worked with suppliers and manufacturers from the USA, UK, Europe, China, Japan, Korea, and Thailand — handling design verification for equipment ranging from simple air receiver tanks to complex petrochemical process vessels.

Which industries does this affect most?

  • Oil & gas
  • Petrochemical
  • Manufacturing — food and general industrial
  • Industrial servicing and maintenance

FAQ

Can I use/import pressure vessels from China?
Yes you can but they need to be designed according the recognised design standards as per the Fourth Schedule of OSH (Plant Requiring Certificate of Fitness) Regulation 2024. 

No. DOSH only recognizes the design codes listed in the Regulation’s Fourth Schedule — most commonly ASME Section VIII. A vessel manufactured in China must still be designed and built to one of these recognized standards, not GB.

Strictly speaking no, but in some circumstances it might be possible but may require extensive reverse engineering and testing. 

As end user, you will not be able to obtain the DOSH Certificate of Fitness (CF) or commonly known as Perakuan Mesin Tekanan (PMT) and this will be a violation to the Section 27B. But don’t worry, do reach out to us and we can discuss the options that you may have to get things right. 

Yes.